Wollongong Seawall
Built in the 19th century, the W7 seawall of Wollongong Harbour is a significant heritage asset for the community of Wollongong. Following MCM’s successful remediation of the W8 seawall in 2015 and nearby W2 seawall in 2016, the NSW Department of Planning & Environment subsequently awarded MCM a third contract to restore the W7 seawall in 2018.
Client Brief
To undertake restoration and remediation works to W7 seawall which safeguard the preservation and protection of the historical asset for decades to come.
What We Delivered:
Careful assessment and specialist experience to ensure the project was correctly resourced and managed to mitigate issues during construction
A coordinated team of specialist stonemason trades
Repair and replacement of damaged stone along the 300m seawall
Repointing of joints
Concrete, civil and landscaping works
Seawall stabilisation
Seamless teamwork and collaboration between all project partners to ensure restoration works completed on time and on budget, without incident and to heritage standards