McElhone Street Rock Wall
Key details
Current status
Rock stabilisation works
Location + Section
55 McElhone Street
Woolloomooloo
Type of work
Wall cliff embankments maintenance
Start date
Monday, 9 October 2023
Duration
1 week – until 13 October 2023
Work hours
7.30am to 5.00pm Monday to Friday
7.00am to 3.00pm Saturday
Contact
Phillip Britten
Community Liaison Officer
0409 075 591
communityliaison@marineandcivil.com.au
Project overview
Rock stabilisation works will take place at 55 McElhone Street. Water filled barriers will be in place to isolate the construction area from pedestrians. During the stabilisation works, rock bolts will be installed and the wall will be shotcreted.
We will work to minimise community impacts during this time, however there will be minor machinery noise during the works.
The safety of everyone is our priority. Thank you for your patience while we complete these important works.