Key details
Current status
Maintenance works are currently in progress
Location + Section
Millers Point
Agar Steps
Type of work
Renewing fencing and steps
Start date
8 January 2024
Duration
until November 2024
Work hours
7.30am to 5.00pm Monday to Friday
7.30am to 3.00pm Saturday
Contact
Phillip Britten
Community Liaison Officer
0409 075 591
communityliaison@marineandcivil.com.au
Project overview
MCM are renewing the palisade fence by taking it offsite for renewal and restoration. A durable paint system will be applied to the steel elements, ensuring this heritage asset's longevity. Any defective or damaged stone will also be replaced with identical sandstone to uphold the heritage values while also improving the structural integrity of the stone wingwalls.
We will work to minimise community impacts during this time, however there will be minor machinery noise during the works.
The safety of everyone is our priority. Thank you for your patience while we complete these important works.
Site location
Agar Steps, plan view
Agar Steps, section